Part 1 of this series worked through the TNERC tariff order line by line against a real 700 kVA HT-I bill from a textile mill in Erode — the 25% ToD peak surcharge, the 5% Electricity Tax, and a Group Captive open-access structure that zeroed out both Cross-Subsidy Surcharge and Additional Surcharge on that same bill. It closed on one open question: how much storage does it actually take to turn that ToD spread into captured value, and what the return on doing it looks like. This article answers that question against the same facility, the same real numbers — no illustrative buyer profile, no rounded-off placeholder figures.

📋 A Quick Orientation Before the Sizing Math This mill runs two separate solar arrangements that shouldn't be conflated. Its own rooftop PV feeds surplus back to TNPDCL under the GISS (Grid-Interactive Solar System) Net Feed-In mechanism — the subject of this article. Separately, the Group Captive open-access supply referenced in Part 1's real bill is a distinct wheeled-in arrangement from an off-site solar asset, which is why that bill shows Cross-Subsidy Surcharge and Additional Surcharge waived. The BESS use case below concerns the first of these — the facility's own rooftop surplus — not the Group Captive import.
Rooftop solar and battery energy storage system at a Tamil Nadu textile mill
01

The Problem: Solar That Peaks at Noon, a Grid That Peaks at 6pm

Rooftop generation and evening demand don't overlap — and Tamil Nadu's banking rules don't bridge the gap

This facility's rooftop solar generates through the middle of the day — peak output between 10am and 3pm — when the mill's own in-process load absorbs only part of it. Whatever exceeds on-site demand is exported to TNPDCL under the GISS Net Feed-In mechanism. Simultaneously, the mill draws its heaviest grid import during the 6–10pm evening peak — exactly when solar generation has already dropped to zero, and exactly the window Part 1 identified as this facility's most expensive electricity: the 25% ToD surcharge plus the 5% ad valorem tax riding on top of it.

A Battery Energy Storage System closes that mismatch mechanically: capture the daytime surplus, hold it, and discharge it into the evening peak instead of letting it export at a fraction of what that same energy is worth avoided at 6pm.

Chart showing Tamil Nadu solar generation curve versus evening peak demand mismatch

Twelve Months of Observed Surplus (Apr 2025 – Mar 2026)

The surplus profile below is the facility's own metered data, not a modelled estimate — the basis for every sizing decision that follows.

Month Total Surplus (kWh) Daily Surplus (kWh/day) BESS-Shiftable (kWh/month) Notes
Apr-2515,568518.915,568Full capture
May-2514,912481.014,912Full capture
Jun-2516,968565.616,968Full capture
Jul-2511,392367.511,392Full capture
Aug-2511,192361.011,192Full capture
Sep-2512,288409.612,288Full capture
Oct-2515,208490.615,208Full capture
Nov-25*16,382546.1*16,382Full capture; estimated
Dec-2518,648601.518,648Full capture
Jan-2617,840575.517,840Full capture
Feb-2622,720811.419,883Capped at 632 kWh/day
Mar-2622,472724.919,592Capped at 632 kWh/day
Annual Total1,95,590 kWh1,92,873 kWh98.6% capture rate

ℹ Source: Facility's own metered generation and export data, Apr 2025 – Mar 2026, supplied by the client.

📊 The Erode Number 98.6% — the share of a full year's rooftop solar surplus a correctly-sized 783 kWh BESS captures. The battery is only capacity-constrained in February and March, precisely when solar export peaks.

02

Sizing the Battery: From Daily Surplus to Installed kWh

Working backward from the dispatch target through DoD and round-trip efficiency

Sizing starts from the target — how much energy needs to reach the evening peak as usable AC output — and works backward through depth-of-discharge and round-trip efficiency losses to the installed DC capacity that delivers it.

ParameterValueBasis
Target Dispatchable Energy632 kWh/day AC outputMatches daily surplus cap and financial model
Depth of Discharge (DoD)95%LFP chemistry benchmark
AC-AC Round-Trip Efficiency (RTE)85%OEM benchmark
Installed Battery Capacity783 kWh3 racks of 261 kWh each
Power Rating (charge/discharge)375 kW3 x 125 kW PCS modules with reserve margin

Sizing formula: Installed kWh = Dispatchable ÷ (DoD × RTE) = 632 ÷ (0.95 × 0.85) = 783 kWh.

Battery sizing flow diagram from dispatch target to installed capacity

Technical Specification

ParameterSpecification
TechnologyLithium Iron Phosphate (LFP) — inherently safe, thermally stable
ConfigurationGrid-interactive, behind-the-meter (BTM)
Installed Energy Capacity783 kWh (DC nameplate)
Usable DC Capacity after DoD743 kWh
AC Output per Cycle632 kWh
Power Rating375 kW (3 x 125 kW PCS modules)
Daily Cycle Utilisation1 cycle/day (solar charge to evening discharge)
Charge SourceRooftop solar surplus (primary); optional night grid top-up
Discharge Window18:00–22:00 IST (TNERC ToD evening peak slot)
ComplianceCEA safety standards; GISS BTM provisions; islanding protection mandatory
ConnectivitySCADA / BMS with remote monitoring
EnclosureOutdoor IP55 containerised or indoor rack-mount

Useful Life

ParameterValue
Manufacturer Design Life6,000 cycles (LFP industry standard)
Effective Cycle Rate1 cycle/day → 365 cycles/year
End-of-Life ThresholdBattery availability ≤ 70% of nameplate

03

The Spread: What Storing Solar Is Actually Worth

Building the avoided-cost stack from Part 1's confirmed rates — not the headline evening-peak rate alone

The value of shifting one kWh of rooftop solar from midday export to evening self-consumption is the gap between two numbers: what that unit is worth avoided at 6–10pm, and what it's worth exported instead. Both numbers need building up from confirmed rates, not read off a single tariff line.

Avoided Grid Cost — Evening Peak, Group Captive Structure

ComponentRateBasis
Energy Charge, incl. 25% ToD Peak surcharge₹9.38/kWhHT-I base ₹7.50 + 25% peak surcharge, TNERC Order No.6 of 2025
Wheeling / Network Charge₹1.04/kWhApplies to all grid-imported units, TNERC Order No.6 of 2025
Cross Subsidy Surcharge₹0.00/kWhWaived — confirmed Group Captive open-access structure per Part 1's real bill
Electricity Tax, 5% ad valorem~₹0.47/kWh5% on taxable energy + peak charges (₹9.38 base)
Total Avoided Grid Cost₹10.89/kWhSum of Wheeling/Network Charge, Electricity Tax, and Energy Charges

ℹ Source: TNERC Tariff Order No.6 of 2025; verified TNPDCL HT-I bill, Erode circle, May 2026.

Foregone Export Value — GISS Net Feed-In

The GISS feed-in tariff last set by TNERC (Generic Tariff Order No.8 of 2021, ₹3.10/kWh for the 151–999 kW band) expired 31 March 2023, with no successor rate located as of this article's publish date. More materially: TNERC's Green Energy Open Access Regulations, 2025 confirm that solar banking in Tamil Nadu is strictly monthly, with no carry-forward — unutilised surplus left over at month-end is bought back at only a fraction of the applicable RE tariff. For a facility that is already exporting more than it can bank or self-consume in several months of the year (see the February–March capacity-capped rows above), a meaningful share of that exported surplus is not being monetised at a stable per-unit rate at all — it is lapsing at month-end. This model treats the foregone export value conservatively as ₹0/kWh rather than applying an unconfirmed ₹3.10 rate to energy that Tamil Nadu's own banking rules don't guarantee gets paid for.

💡 Net Arbitrage Spread (Year 1) ₹10.89/kWh — avoided grid cost of ₹10.89, less a GISS export value treated as ₹0 due to Tamil Nadu's monthly-lapsing banking rule.
Diagram showing the spread between avoided grid cost and solar export value
📊 The Erode Number ₹51,495 — what Part 1's real May 2026 bill showed the 25% ToD peak surcharge alone added to this facility's monthly cost. That same surcharge, run in reverse, is the value a BESS captures by discharging into that window instead.
⚡ Tamil Nadu HT-I Facilities
This mill's ToD surcharge alone runs ₹51,495/month — before any GISS export lapses on top.
See What Your Own Bill Is Losing to the Evening Peak

PWRNXT builds this same avoided-cost stack against your actual HT tariff category and metered surplus — not a template rate card.

Get a Free Feasibility Study →

Free analysis · No obligation

💬 WhatsApp Us

Reply within 4 business hours

Regulatory Posture: Mostly Carrot, One Structural Stick

Tamil Nadu's storage-relevant framework leans opportunity, not compliance:

  • The 25% peak / −5% night ToD spread (TNERC Order No.6 of 2025) directly rewards load-shifting — a carrot that applies automatically to every ToD-metered HT consumer, no separate application required.
  • BESS behind-the-meter is explicitly permitted under the GISS Regulations, 2021, subject to CEA safety standards and mandatory anti-islanding protection — no special storage-specific approval process beyond standard GISS registration.
  • The Draft GISS Regulations, 2024 (under TNERC consultation as of this article's publish date) are expected to formally cover BESS-coupled solar and group/virtual net metering — a signal of regulatory direction, not yet a finalised rule.
  • The one stick-like element: monthly-only banking with no carry-forward (Green Energy Open Access Regulations, 2025) doesn't penalise storage directly, but it removes the alternative — a facility can't simply bank its way around a mismatched generation/demand curve the way it could in a state with annual carry-forward. That structural fact is what pushes the economics toward storage rather than banking.

A note on precision: this article cites TNERC order and regulation numbers by name and number throughout, drawing on the same primary source Part 1 verified (TNERC Tariff Order No.6 of 2025) plus the GISS Regulations 2021/2024 as summarised in PWRNXT's internal facility assessment. Exact clause-level text for the BESS-specific GISS provisions was not independently re-verified against the regulation PDF for this article and should be confirmed before this framing is used in a client-facing regulatory opinion.

GST and Fiscal Treatment

ItemGST RateNotes
Solar Power Generating System (composite EPC)5%Covers goods + services under composite supply
BESS supplied as part of solar+BESS EPC5%When structured as integral part of renewable energy generating system
BESS supplied standalone / retrofit18%Standard battery rate — avoid this structure
Accelerated DepreciationEligibleRenewable energy assets qualify for higher depreciation under Income Tax Act
MNRE / State SubsidyNot applicableCapital subsidies are residential-only; C&I consumers ineligible

Recommendation: structure the solar+BESS system as a single composite EPC contract to secure the 5% GST rate rather than the 18% standalone-battery rate.


04

The Economics: Capital Cost, Savings, and Payback

A 15-year model built on the corrected ₹10.89/kWh spread

Capital Cost

ParameterValue
Installed BESS Capacity783 kWh
All-in CapEx₹1.25 Cr (ex works, fully installed system; excludes civil works at site)
GST Treatment5% (composite solar+BESS EPC — see Section 03)
O&M3% of CapEx p.a., escalating at 5% p.a.

Exclusions: civil works, foundation, trenching beyond agreed scope, statutory utility charges, and any owner-specific enabling works unless expressly included in the final EPC scope.

Year 1–15 Savings

Built on the corrected ₹10.89/kWh Year-1 spread (Section 03), the same battery-availability degradation curve as the technical model (Section 02), and 3% p.a. tariff escalation — conservative against Tamil Nadu's historical 4–5% trend.

YearGross Savings (₹L)DG Replacement Savings (₹L)O&M (₹L)Net Savings (₹L)Cumulative Net (₹L)
120.9911.033.7528.2728.27
221.2011.033.9428.2956.56
321.4111.034.1328.3184.87
421.6111.034.3428.30113.17
521.8011.034.5628.27141.44
621.9811.034.7928.22169.66
722.1411.035.0328.14197.80
822.2911.035.2828.04225.84
922.4411.035.5427.93253.77
1022.5711.035.8227.78281.55
1122.6911.036.1127.61309.16
1222.8011.036.4127.42336.58
1322.8811.036.7327.18363.76
1422.9711.037.0726.93390.69
1523.0411.037.4226.65417.34

ℹ Source: PWRNXT internal 15-year BESS financial model, built on TNERC Tariff Order No.6 of 2025 rates and the facility's metered surplus/diesel data.

Simple Payback: ~4.4 years (crossed within Year 5)

📊 The Erode Number 417.34 — the 15-year net savings, in ₹ lakh, this model produces against a ₹125 lakh all-in CapEx. A 3.3x return on capital over the project's 15-year hard-cap life.
Chart showing cumulative BESS savings crossing the capital payback threshold

DG Replacement / Diesel Displacement

The client's own operating data shows annual diesel consumption of 11,760 litres at ₹93.77/litre — ₹11.03 lakh/year of diesel expense. At an assumed genset yield of 3.4 kWh/litre, that's approximately 39.98 MWh/year of diesel-derived energy the BESS can potentially displace through EMS-controlled coordination of PV, DG, and grid. This is modelled as a secondary value stream, additive to the solar-arbitrage case above, not a substitute for it.

Additional Value Streams (Qualitative)

  • HT Demand Charge Reduction (Peak MDI Shaving): discharging during the 15-minute MDI integration window can reduce the recorded Maximum Demand Indicator. At the current ₹608/kVA/month demand charge, even a 50–100 kVA reduction generates meaningful additional savings on top of the ToD arbitrage modelled above. This stream can be quantified based upon 15-minute interval load data from the client's TNPDCL meter.
  • Night-Rate Grid Top-Up During Monsoon: in months where daily solar surplus falls below the 632 kWh/day AC cap, unused BESS headroom can charge from the grid at the ₹7.13/kWh night rate and discharge into the ₹9.38/kWh peak window — an incremental spread of roughly ₹2.25/kWh, adding monsoon-month arbitrage value with no new infrastructure.

05

Investment Summary

The base case, at a glance

783 kWh
Installed BESS capacity, 375 kW power rating
₹125L
All-in CapEx, ex works
3.3x
Return on capital over 15 years
MetricBase Case
Installed BESS783 kWh / 375 kW
All-in CapEx (ex works)₹125 lakh
Annual Net Savings (Y1)₹28.27 lakh
15-Year Net Savings₹417.34 lakh
Simple Payback~4.4 years
Payback with accelerated depreciation~3.7 years
Net Savings / CapEx Ratio3.34
CO2 Avoided (indicative)~170 tCO2/year versus grid average emission factor

Why Now

  • TNERC's ToD framework is live and evening-peak pricing already applies to every HT-I consumer — the spread this model captures exists today, not on a future regulatory trigger.
  • LFP BESS economics are commercially viable at C&I scale, evidenced by this facility's own sub-5-year payback.
  • A composite solar+BESS EPC structure secures the 5% GST rate rather than the 18% standalone-battery rate — a fiscal lever that closes as soon as the two are procured separately.
  • Acting under current GISS provisions establishes a pilot ahead of the Draft GISS Regulations, 2024 formalising BESS-coupled solar rules.
  • A successful Erode deployment is directly replicable across other Tamil Nadu facilities on the same HT-I / GISS structure.

FAQ

Frequently Asked Questions

The questions we hear most from Tamil Nadu C&I facilities evaluating this same sizing and spread model.

How was the 783 kWh battery size determined? +
Working backward from a 632 kWh/day AC dispatch target (matching the facility's daily surplus cap) through 95% depth-of-discharge and 85% round-trip efficiency: 632 ÷ (0.95 × 0.85) = 783 kWh installed DC capacity, split across 3 racks of 261 kWh with 375 kW of PCS power.
Why is the GISS feed-in tariff treated as ₹0 in the spread calculation? +
Two reasons. First, the last confirmed GISS feed-in rate (₹3.10/kWh) comes from an order that expired in March 2023, with no successor rate located. Second, and more structurally: TNERC's Green Energy Open Access Regulations, 2025 confirm Tamil Nadu's solar banking is strictly monthly with no carry-forward — so exported surplus a facility can't bank or self-consume within the same billing cycle isn't reliably monetised at a stable rate at all. Treating it as ₹0 is the conservative choice, not an assumption that export is worthless in every case.
How does the GST treatment affect this model? +
Structuring the solar and BESS system as a single composite EPC contract secures a 5% GST rate under current treatment, versus 18% if the battery is procured as a standalone retrofit. This model assumes the composite structure; a standalone procurement would materially change the CapEx-inclusive-of-tax picture.
What changes if this facility weren't Group Captive? +
The avoided-cost stack in Section 03 excludes Cross-Subsidy Surcharge because this facility's real bill confirms a Group Captive waiver. A non-Group-Captive, third-party open-access facility on the same HT-I category would add ₹1.99/kWh CSS (and, per Part 1, an Additional Surcharge with a rate that should be confirmed against TNPDCL's current open-access billing circular) back into the avoided-cost stack — which would widen the spread, not narrow it, since that charge only applies to grid-imported units, the same units the BESS is designed to avoid.
Is the diesel-displacement saving guaranteed alongside the solar-arbitrage saving? +
It's modelled as additive but depends on EMS strategy and site operating practice — the BESS has to be configured and dispatched to prioritise DG replacement in addition to its primary solar-shifting role. Treat it as a secondary value stream that requires deliberate configuration, not an automatic byproduct of installing the battery.

The Synthesis: How Much Storage, and What It's Worth

Part 1 asked what Tamil Nadu's tariff structure actually costs a facility that doesn't shift its load. This article answers the other half: for a real 700 kVA HT-I mill in Erode, closing that gap takes a 783 kWh / 375 kW battery, costs ₹125 lakh installed, and pays back in under 4.5 years on a spread that holds up even under a conservative, zero-value treatment of the facility's own solar exports.

The two structural facts driving that number aren't going away: Tamil Nadu's ToD surcharge applies automatically to every HT consumer today, and its monthly-only banking rule means unshifted solar surplus has nowhere to go but a discounted or lapsed export. Storage is the only lever that converts a facility's own generation curve into its own consumption curve — banking rules and export tariffs can't do that job in Tamil Nadu the way they might in a state with annual carry-forward.

🔋 BESSaaS — Zero Capex Operating Lease
This Facility's Numbers Came From Its Own Bill — Not a Template

This facility's 783 kWh / 375 kW sizing, spread, and payback came from its own real bill and its own metered surplus data — not a template. PWRNXT models the same for any Tamil Nadu HT facility as part of a free feasibility study, at zero capex.

₹0 capex — operating lease Sized to your ToD load profile 5-day feasibility study
See the Lease Model →

Free · 5 working days · No capex commitment

💬 WhatsApp Us

In This Series

Part 1: Tamil Nadu C&I Tariff Decoded — TNERC HT I–V rates, ToD mechanics, and the Group Captive waiver this article builds on.

Get Your Own Facility's ₹10.89/kWh Number

PWRNXT engineers a free BESS feasibility study for your Tamil Nadu facility — sized to your load profile, tariff category, and solar capacity. Verified saving figure in 5 business days. Zero cost, zero obligation.

Disclaimer: This article is for informational purposes only and does not constitute financial, regulatory, or investment advice. Figures are drawn from TNERC Tariff Order No.6 of 2025 (effective 1 July 2025), TNERC Generic Tariff Order No.8 of 2021 (GISS feed-in tariff, expired 31 March 2023 — no successor rate independently confirmed), TNERC GISS Regulations 2021, the Draft GISS Regulations 2024 (under consultation), TNERC Green Energy Open Access Regulations, 2025, and the verified 700 kVA HT-I TNPDCL bill (Erode circle, May 2026) referenced in Part 1 of this series, as of this article's publish date. The client's underlying facility identity, GSTIN, and account details have been withheld throughout; solar surplus and diesel operating data were supplied by the client for Apr-25 to Mar-26. BESS degradation follows a standard LFP calendar-and-cycle composite model, to be replaced with OEM-specific data at detailed design stage. The GISS feed-in tariff is treated as ₹0 in this model as a conservative assumption, not a confirmed current rate — readers relying on export revenue in a similar facility's model should confirm the current applicable rate before finalising. Regulatory language is often subject to differing interpretation — flag corrections to contact@pwrnxt.in and we will review and update this article accordingly.